Ofgem wants to charge datacentres for grid access

The refundable fee is intended to stop ‘speculative’ projects

3D illustration of server room in data center full of telecommunication equipment,concept of big data storage and cloud

Image:
There are more than 300 datacentres waiting for grid connections in the UK today

Datacentre developers could be required to make hefty upfront payments to secure access to the UK’s electricity grid, under new proposals aimed at preventing speculative projects from clogging the connection queue.

Energy regulator Ofgem has launched a consultation on plans to introduce a new Data Centre Commitment Fee, saying that developers with genuine plans to build should not be delayed by projects that reserve grid capacity without progressing.

The proposed reforms are at least part-prompted by surging demand for electricity as AI infrastructure grows, placing increasing pressure on a grid already struggling to connect renewable energy projects, housing developments and public services.

New fees aimed at speculative projects

Under the proposals, large datacentre operators would pay a refundable fee when accepting a grid connection offer.

The payment would be returned once a project is successfully connected to the electricity network, but forfeited if the developer withdrew before completion.

Ofgem said the charge would range from £237,500 to £712,500 per megawatt, equivalent to around 2.5% to 7.5% of an average project's cost.

While we don’t have GW-scale datacentres like the USA, the largest UK facilities still draw more than 70MW of power. A new datacentre of this size could expect to be on the hook for between £16.6 million and £49.9 million.

Developers would also have to meet a series of mandatory construction milestones before their planned connection date or risk losing their place in the queue.

Ofgem said the measures were intended to ensure scarce grid capacity is allocated to projects that are ready to proceed rather than those preserving future options.

Eleanor Warburton, Ofgem's Director for Energy System Design and Development, said Britain's electricity connections queue had more than tripled in less than a year.

"Consumers should not bear the risks created by speculative projects taking up space in the system," she said.

AI ambitions driving surge in electricity demand

There are currently 315 datacentres waiting for grid connections, says Ofgem, representing around 73GW of electricity demand.

That figure has risen by almost 50% over the past year and exceeds Britain's peak national electricity demand (around 45GW) by almost 30GW.

While some developers are exploring private on-site power generation to avoid lengthy waits for grid access, most continue to seek permanent connections to the national network.

The National Energy System Operator estimates Britain's datacentre capacity could reach between 3.7GW and 6.7GW by the end of the decade, while the government's Compute Roadmap sets a target of at least 6GW of AI-capable datacentre capacity by 2030.

Wider reforms to ease pressure on the grid

The proposals are part of broader efforts to reduce longstanding delays in connecting projects to Britain's electricity network.

Last year, the government-owned National Energy System Operator introduced reforms that removed hundreds of inactive or speculative energy projects from the connections queue.

Ofgem said similar action was now needed for datacentres, although determining future capacity requirements is more complex because of uncertainty over how much AI infrastructure the UK will ultimately require.

The consultation also follows growing debate over the energy impact of the expanding datacentre sector.

A report published in May by the International Data Center Authority estimated that datacentres now account for around 6% of electricity consumption in both the UK and the United States.

Earlier this month, the Scottish National Party's national council backed a motion calling for a temporary pause on new datacentre developments that have yet to receive planning permission.