UK nuclear overhaul urged to tackle datacentre boom
A ‘once in a generation opportunity'
The UK has been urged to overhaul its nuclear approval system after a report found the country now leads the world in reactor construction costs.
The Nuclear Regulatory Taskforce, led by former Office of Fair Trading chief and UKRI board member John Fingleton, released its findings [pdf] Monday, calling for a "radical reset" of the UK's nuclear approvals system.
The review, commissioned by Prime Minister Sir Keir Starmer, argues that decades of "overly complex" regulation, fragmented oversight and a culture of risk aversion have driven up costs and slowed construction compared with rival nations.
"This is a once in a generation opportunity," Fingleton wrote.
"The problems are systemic, rooted in unnecessary complexity and a mindset that favours process over outcome."
The report lays out 47 recommendations across five broad areas, including clearer government leadership, streamlined approvals, reduced risk aversion and stronger incentives for timely delivery and innovation.
The headline proposal is the creation of a Commission for Nuclear Regulation, a new unified decision maker intended to cut through overlapping regulators, planning authorities and environmental bodies.
This "one-stop shop" approach, the Taskforce argues, would make projects faster and cheaper without reducing safety.
The document also urges comprehensive reforms to environmental and planning rules, echoing earlier government moves to accelerate datacentre construction.
These include:
- Amending the cost cap for judicial reviews and limiting legal challenges for Nationally Strategic Infrastructure Projects
- Indemnifying nuclear developers who continue work while legal challenges proceed
- Modifying the Habitats Regulations, which protect vulnerable species and natural sites, to reduce compliance costs
- Revising worker radiation limits, which the report calls "overly conservative" and far below levels considered "broadly acceptable"
These proposals are expected to trigger debate among environmental groups and unions, which have long warned against weakening ecological protections or workplace safety standards.
Britain currently operates nine nuclear reactors, generating roughly 15% of the country's electricity in 2024. But eight of these facilities are scheduled to shut down by 2030, leaving a widening supply gap as the UK simultaneously promises major decarbonisation gains.
The UK is among the 30 signatories of a global pledge to triple nuclear capacity by 2050, a target the review says will be impossible without major regulatory reform.
While dozens of countries worldwide are launching or expanding reactor programmes, Britain has struggled for decades to bring new stations online at pace or at predictable cost.
The government hopes to kick-start a new build wave, including its recently announced first nuclear plant powered by small modular reactors (SMRs). But the SMR facility is not expected to generate electricity until the mid-2030s, leaving at least a decade of constrained supply.
AI boom fuels calls for growth
The regulatory overhaul coincides with what officials describe as an unprecedented surge in electricity demand, driven by the rapid expansion of datacentres and AI supercomputing under the UK's AI Opportunities Action Plan.
National Grid has warned that datacentre power consumption is on track to rise 500% over the next decade, intensifying the need for reliable baseload power.
Until new nuclear capacity arrives, analysts expect datacentres to rely heavily on a mix of gas turbines and renewable sources such as wind and solar, an arrangement that may complicate carbon targets and force costly grid upgrades.
Commenting on the report Ben Cooney, Chief AI & Innovation Officer at the Tony Blair Institute, said: "This report is clear: Britain cannot deliver its energy, security or growth ambitions with a 20th-century regulatory machine.
"Britain once led the world in nuclear; now we lag far behind. To get back on track, we must cut energy costs and unlock our industrial and AI capacity to power our future - and we must deliver quickly."