Datacentre 'picks and shovels' lose $4.2tn as AI build-out jitters spread

Industrial suppliers have lost almost half their gains from the past year

Companies supplying the AI data centre build-out have lost about $4.2tn since June, wiping out almost half of the $9.4tn they gained in the previous year, as investors worry about debt-funded spending, delays and political backlash.

An analysis by The Financial Times has found that the value of companies strongly associated with data centre construction have decreased significantly during the second half of this year.

Global manufacturing, utility and mining companies have lost approximately $4.2tn in value since June as investor confidence has ebbed – slowly at first but then rather more quickly in the last four weeks.

These companies have been likened to the “picks and shovels” of the AI trade, along with chipmakers and includes companies such as Caterpillar, which supplies gas generators to datacentre construction sites and Okto, which signed a contract with Meta to supply nuclear power to a campus Meta is developing in Ohio.

The FT analysis shows that losses for these businesses over the second half of this year wiped out almost half of the $9.4tn in value that they gained during the previous 12 months.

A series of unfortunate events

The sell off comes at a difficult time for AI-linked stocks. Capital markets seem to finally be reaching the limits of their tolerance for ever expanding debt-financed capital expenditures at hyperscalers. US midterm results – which were driven strongly in states like Texas, Ohio and Iowa by concern about the impact of datacentre construction - also brought about some serious market jitters and the last few days have brought revelations that a substantial proportion of Nvidia revenues might well have come from sales to companies and organisation in China blacklisted by the US. The extent of involvement of various departments and individuals within the Trump administration is still the subject of multiple ongoing journalistic enquiries.

These events have combined to exert downward pressure on chipmaker stocks including AMD, Micron. Broadcom and TSMC but also manufacturers Super Micro Computer, Dell and HPE and neoclouds Coreweave and Nebius, Industrial companies whose fortunes have become ever more closely intertwined with the AI build out are now also being viewed with increasing nervousness from investors.

The sector has been the second-worst-performing in the S&P 500 since the summer, second only to technology. Vertiv makes power and cooling systems for data centres and despite its third-quarter sales rising 61% to $4.31bn and orders more than doubling, shares fell 23% in the week after the midterms. Stock has rallied since but at $202.07, shares are about 46.8% below the peak of $379.94 in May.

Projects under pressure as backlash builds

Dan Thompson, an analyst with 451 Research at S&P Global Energy estimates that roughly two-thirds of the projects being tracked by S&P Global face delays varying from straightforward construction delays to more politically driven community opposition, impending state regulation or outright moratorium. The group is tracking 157 projects that have been paused, severely delayed or abandoned. Quoted in Politico he said:

“This is considered a key risk for projects that are in flight,” Thompson said on a webinar last week. “It’s across the country that we’re seeing this. We’re seeing pushback and challenges to data center development.”

Sightline Climate analysts estimate that 30–50% of US AI data centres planned for 2026 will be delayed or cancelled. About 16 GW is due this year, but only around 5 GW is under construction.

Other analysts remain bullish, arguing that the financial fundamentals of these businesses are solid and that demand will continue to outrun supply. Alex Cordovil, an analyst at Dell’Oro Group says:

“In terms of the fundamentals of revenues and the potential earnings for these companies, we are still looking at a very strong prospect. The build-out is not decelerating as of yet.”

He continues: “Backlogs are at record highs, meaning that until 2027 ... revenue growth is already baked in.”

For now, the politics of datacentre construction in the US remain an open question. Voters have certainly made their views clear, and Democrats now hold Congress and are moving into governors mansions in several key states.

But we simply won’t know until well into 2027 how much the campaign pledges and tough talk will translate into moratoriums, more robust rules and environmental protections or greater accountability for the tech sector. Only then will we see the impact on the companies supplying the build-out.