28 Mar 2006
Problems implementing the Foreign Office's Prism computer system included incorrect programming that prevented 20 overseas posts, including British Embassies in Moscow and New Delhi, from using it.
When the system went live in February, the embassies and consulates affected
discovered they could not access suppliers, approve purchases or buy goods and
services, and software rules granting access to accounting systems were
incorrect.
The blunders were revealed in reply to questions in the Commons from Labour MP
Andrew Mackinlay, who was told it took two weeks to get our people involved in
missions in places such as Afghanistan online.
Diplomats were told to do their accounts on spreadsheets for a month and submit them to London where they were loaded into the system.
Foreign Secretary Jack Straw said: 'An investigation has been initiated into how these configuration problems arose, and how the issues were resolved subsequently.'
The Foreign Office has also admitted problems with communications for Prism when changes in infrastructure improved the speed and consistency of performance of 67 posts connected to London by landline, but didn't reach a further 112 posts that rely on satellite communications.
Straw said the Foreign Office 'maintains a close and constructive dialogue' with systems supplier Capgemini but said it 'would not be appropriate' to reply to Mackinlay's further question about the department making a claim against Capgemini for lack of sufficient memory in the system because of 'the ongoing nature of discussions'.
The Foreign Office was strongly criticised earlier by the Commons Foreign Affairs Committee for late delivery of its annual report and accounts partly because of problems with Prism.
Have your say on this article
Newsletters
Latest stories from Public Sector
Latest videos
You may also like
Public Sector jobs
Technology Patent Wars
Case studies from large organisations across all sectors
... And rich media, and flexible working, and peaks in traffic ...
Upcoming Events
Join us for this Computing web seminar, in which the Head of BI at the Co-operative Group Nick Colebourn will be explaining just how he reigned in the Group’s sprawling database estate and how significant savings were realised and data quality improved as a result.
Date: 31 May 2012
Time: 11:00 AM
Live June 13th 11:00am: Register now. During this web seminar we will be looking at the sorts of incidents that can bring data centres grinding to a halt and what can be done about them.
Date: 13 Jun 2012
Time: 11:00 am
Receive the latest jobs direct to your inbox
Are you being paid what you are worth?