06 Aug 2003
The Inland Revenue disregarded Whitehall's official quality assurance process when developing its disastrous Tax Credits IT system.
The Gateway Review process is meant to be mandatory, particularly for high-risk 'big bang' projects like Tax Credits that have a single go-live date for the whole system.
Further reading
But sources close to the project told Computing the Revenue skipped the first three stages - called Gateway zero, one and two - which cover essentials such as business justification and procurement strategy.
The six-stage process, overseen by the Office of Government Commerce (OGC), is designed to monitor projects at key stages to guard against failure.
Paymaster General Dawn Primarolo told the BBC's Inside Money programme last month that the Revenue was not warned about problems with the IT, and that the project had the OGC's full sanction.
'The report that [the OGC] did on our readiness going into April was that it was an exemplary example,' she said.
But the OGC was not involved with Tax Credits until the end of last year - at Gateway level three, the final milestone before the system goes live - when it was too late to make significant changes.
Deapite the Gateway process being mandatory, the OGC still needs to be invited in by departments running projects and does not have the power to take the initiative itself.
An Inland revenue spokeswoman said: 'The Inland Revenue agreed with OGC that a review would be undertaken and would focus on programme governance in its widest sense.
'As a result of the review, which found that the Programme was an exemplar of good programme management, the Revenue was able to move on to Gateway Four.'
According to a report this week by the Parliamentary Office of Science and Technology, the OGC considers Gateway Zero to have had particular impact on improving the success rate of government IT projects.
'It is compulsory and expected at the start of a programme and is recommended for high-risk projects,' says the report.
The Tax Credits system, implemented by EDS, was launched in April to coincide with the new tax year.
System downtime and slow response times created massive backlogs of applications and caused chaos for families applying for the credit.
Have your say on this article
Newsletters
Latest stories from Public Sector
Latest videos
You may also like
Public Sector jobs
Technology Patent Wars
Case studies from large organisations across all sectors
... And rich media, and flexible working, and peaks in traffic ...
Upcoming Events
Join us for this Computing web seminar, in which the Head of BI at the Co-operative Group Nick Colebourn will be explaining just how he reigned in the Group’s sprawling database estate and how significant savings were realised and data quality improved as a result.
Date: 31 May 2012
Time: 11:00 AM
Live June 13th 11:00am: Register now. During this web seminar we will be looking at the sorts of incidents that can bring data centres grinding to a halt and what can be done about them.
Date: 13 Jun 2012
Time: 11:00 am
Receive the latest jobs direct to your inbox
Are you being paid what you are worth?