17 Oct 2006
The National Audit Office (NAO) has urged the Ministry of Defence to reconsider the way it manages IT-based acquisitions in the light of continuing delays and cost increases affecting the £2.4bn Bowman military radio and combat infrastructure platform (CIB).
In a new report, the NAO says that traditional approaches to equipment purchase, with development, production and support combined with one or more mid-life upgrades, will not deliver the desired capability in a timely manner or to an acceptable cost.
The report says Bowman CIP should be managed ‘as a programme where continual evolution and refreshment are the norm.’
Keeping to traditional specific time and cost parameters based on the idea of a project reaching a conclusion is difficult for a project in a state of continual development, says the NAO.
Bowman CIP will replace the antiquated Clansman radio network dating from the 1970s. The NAO says the project has been ‘recast’ to include an additional £121m and has a further unspecified delay until 2007.
But the report also says that initial versions of Bowman and CIP have started to deliver benefits to UK armed forces on operations in Iraq and Afghanistan.
‘The secure voice radios and equipment showing the position of units has performed well and soldiers have growing confidence in them,’ says the report.
Further reading:
Have your say on this article
Newsletters
Latest stories from Public Sector
You may also like
Public Sector jobs
Technology Patent Wars
Case studies from large organisations across all sectors
... And rich media, and flexible working, and peaks in traffic ...
Upcoming Events
Join us for this Computing web seminar, in which the Head of BI at the Co-operative Group Nick Colebourn will be explaining just how he reigned in the Group’s sprawling database estate and how significant savings were realised and data quality improved as a result.
Date: 31 May 2012
Time: 11:00 AM
Live June 13th 11:00am: Register now. During this web seminar we will be looking at the sorts of incidents that can bring data centres grinding to a halt and what can be done about them.
Date: 13 Jun 2012
Time: 11:00 am
Receive the latest jobs direct to your inbox
Are you being paid what you are worth?