18 Sep 2008
Like many of the councils that struggled to meet the original 31 March deadline for the phase 1B implementation of the Integrated Children’s System (ICS), Redbridge Council has put huge effort into delivering a compliant system.
The authority went live with its ICS system in April 2008, just 15 weeks after signing the procurement agreement with supplier LiquidLogic for the Protocol ICS system.
The system combines services from education and children’s social care into
one integrated service and has 250 users at The
Redbridge Pathfinder
Children’s Trust.
Like many councils, children make up a significant percentage of Redbridge’s
population. It is predicted that by 2016, 14 per cent of the population of this
outer-London authority will be under 18, so building a system able to serve this
growing population has been a priority.
The council was able to fast-track the system deployment by appointing a lead social care practitioner to act as a link between the staff who implemented the system and those using it. This ensured that users of the system were offered support and training, while guaranteeing that any issues that arose particularly ones involving elements of professional practice could be quickly addressed.
“It now means that we have met the government’s targets for compliance with ICS, which means our social care staff have a system that will safeguard children in Redbridge,” says Carole Brown, head of resources at Redbridge Children’s Trust.
Following the success of the ICS rollout, Redbridge has begun work on implementing its electronic Common Assessment Framework (eCAF), another central pillar of the government’s Every Child Matters agenda. Redbridge expects to go live with that system later this year.
“We are now ahead of the game, not only in terms of ICS, but also in the facilitation of increased multi-agency working,” says Brown.
Have your say on this article
Newsletters
Latest stories from Public Sector
You may also like
Public Sector jobs
Technology Patent Wars
Case studies from large organisations across all sectors
... And rich media, and flexible working, and peaks in traffic ...
Upcoming Events
Join us for this Computing web seminar, in which the Head of BI at the Co-operative Group Nick Colebourn will be explaining just how he reigned in the Group’s sprawling database estate and how significant savings were realised and data quality improved as a result.
Date: 31 May 2012
Time: 11:00 AM
Live June 13th 11:00am: Register now. During this web seminar we will be looking at the sorts of incidents that can bring data centres grinding to a halt and what can be done about them.
Date: 13 Jun 2012
Time: 11:00 am
Receive the latest jobs direct to your inbox
Are you being paid what you are worth?