Medical staff study a PC screen
Fujitsu has been fired from NHS National Programme for IT

Fujitsu fired from NHS National Programme for IT

Contract renegotiations break down as NHS continues supplier squeeze

Written by Tom Young

The £12.7bn National Programme for IT (NPfIT) was hit by another setback yesterday as one of the three key suppliers to the project was fired.

Fujitsu – which was responsible for the southern area of the scheme – has been fired by the NHS after 10 months of contract re-negotiations broke down.

NHS Connecting for Health (CFH), which runs the NPfIT, insisted the move was in the best interests of the taxpayer.

"Regrettably and despite best efforts by all parties, it has not been possible to reach an agreement on the core Fujitsu contract that is acceptable to all parties," said a spokesman.

"NHS CFH has to continue to protect the interests of the taxpayer and preserve the basis of contracts which ensure payment on delivery."

The NHS CFH supplier contracts work on a strict "payment by delivery" basis.

It is understood that the NHS were demanding more flexibility in Fujitsu's services – Fujitsu wanted more money to provide this flexibility.

Fujitsu is the second major supplier to drop out of the programme after Accenture exited in 2006 citing profitability issues.

CFH says work has started immediately on planning the necessary arrangements to replace Fujitsu.

It is thought BT is the most likely candidate to take over the area as the patient record software being used in London – the area BT supplies – is the same as in the southern region that Fujitsu was supplying.

The other likely option is CSC.

But CSC already runs two of the five areas of the Programme, and has also recently been selected as a preferred supplier for the ID cards programme.

And a switch to CSC would probably mean installing iSoft's Lorenzo software in the Southern region, rather than the Cerner Millenium software BT is familiar with.

reader comments

related articles

British Medical AssociationGovernment

Deadlines too tight for NHS IT

Government blamed for four year delay to part of NHS IT system 21 May 2008

 

Patient records cause four-year NHS IT delay

Other parts of the scheme are broadly on track, but software delays mean care records will be four years late, says NAO 16 May 2008

Politics pushing NHS scheme

Early adopters felt under pressure as Connecting for Health pushed the project forward to meet targets 15 May 2008

NHS must learn lessons on centralised patient records

Programme so far has not focused enough on social aspects of the technology change 06 May 2008

NHS trusts opt for one log-in

Hospitals introduce system to cut password burden 24 Apr 2008

NHS given six months to get IT right

Local trusts must be given autonomy if central approach is still not working in six months, say MPs 27 Jan 2009

NHS trusts not allowed to seek alternative patient record systems

Department of Health rejects MPs calls for six-month deadline on rollout of summary care records 14 Apr 2009

NHS IT suppliers given seven months to get it right

Department of Health CIO sets deadline for BT and CSC to make progress on care records system 28 Apr 2009

related whitepapers

today's top stories

How to maximise the value of your IT networking investment

A panel of experts discuss networking strategies that deliver real value to business 03 Jul 2009

Habitat gets a web site makeover

The furniture retailer is revamping its online presence to provide a fully transactional web site. CIO Jacques Dekock explains why 02 Jul 2009

Government aims to bolster UK's cyber defences

Is the UK’s first national cyber security strategy up to the task of co-ordinating the country’s response to digital threats? Computing investigates 02 Jul 2009

Focus resources on what really matters

IT has become too caught up in the drive for efficiency, at the expense of business success 02 Jul 2009

From tracks man to tax man

Phil Pavitt, outgoing chief information officer for Transport for London, talks to Rosalie Marshall about the lessons he will take to his new role at HMRC 02 Jul 2009

Advertisement

Newsletter signup

Sign up for our range of FREE newsletters:

More available - click 'submit' to view

Existing User

Newsletter user login:

Advertisement

Jobs

Related jobs

Job of the week

Job alerts

Sign up here

Find your next job

IT Salary Checker

Check salary here

Advertisement

White papers

Search white papers

Top categories

VPN, Extranet and Intranet Solutions

WAN/ LAN Solutions

Network Security

Interoperability-Connectivity

Grid/ Utility Computing

Latest poll

Would you use social networking sites to look for a job?

Would you use social networking sites to look for a job?

Tell us what you think about job hunting through LinkedIn, Facebook, Twitter etc

View poll results

Latest audio and video articles

network cablesVideo

How to maximise the value of your IT networking investment

A panel of experts discuss networking strategies that deliver real value to business 03 Jul 2009

green footprintsVideo

How to manage enterprise energy use - and the role IT can play

A panel of experts explore how firms can get to grips with their carbon footprint and make smarter use of energy 01 Jul 2009

Latest in-depth articles

Phil PavittAnalysis

From tracks man to tax man

Phil Pavitt, outgoing chief information officer for Transport for London, talks to Rosalie Marshall about the lessons he will take to his new role at HMRC 02 Jul 2009

UPS worker making a deliveryAnalysis

Global standardisation delivers benefits at UPS

Delivery giant sees benefits of central IT solution 02 Jul 2009

Advertisement

Primary Navigation