Libra project goes £134m over budget

Magistrates' Court's IT is 'shocking waste of money, says MP

Written by Sarah Arnott

The Lord Chancellor's Department's troubled Libra project will cost £134m more than originally anticipated, according to a report by the National Audit Office (NAO).

Libra was designed to provide a standard IT system for Magistrate's Courts including upgraded infrastructure, office automation facilities, a national casework application and electronic links with other criminal justice agencies such as the Crown Prosecution Service.

The original £184m private finance initiative contract was awarded to ICL in 1998 but the implementation was dogged with problems and the deal collapsed in July last year.

ICL - now Fujitsu Services - was left with responsibility for just the infrastructure part of the project, with separate contracts to be awarded for the software and systems integration work.

After re-negotiations last summer, the infrastructure is costing £232m over 8.5 years. The software and systems integration contracts are expected to cost £86m, bringing the total cost to £318m over 8.5 years.

Public Accounts Committee chairman Edward Leigh says Libra is one of the worst IT projects he has ever seen.

'Not only has the cost more than doubled since the original bid but the system will be available for two years less than originally planned. This is a shocking waste of money,' he said.

The NAO report says that the important lesson to be learned is the need for technology projects to run alongside business process changes.

'IT system changes should be planned to support redesigned business processes. Undertaking one without the other is unlikely to deliver value for money,' it said.

'The Department needs to plan ahead now for the IT systems to replace Libra and other court systems where the contracts are due to end in 2007.'

Tags:

reader comments

related articles

Public Sector 2002

Public Sector 2005

26 Jun 2004

 

Accenture wins final part of Libra project

Magistrates' courts deal brings total bill for IT projects to over £300m 28 Oct 2003

Whitehall blames suppliers for IT failures

'Lying' vendors must start delivering projects on time - or else 02 Apr 2003

Offender database a "masterclass" in sloppy management

Project to track all criminals in the UK from sentence to release is three years overdue and has increased in cost from £234m to £690m 12 Mar 2009

Courts' IT system under fire

20-year-old Crest system still requires information to be re-keyed, says NAO 09 Mar 2009

Whitehall slammed for poor IT contract management

National Audit Office says savings of £290m were easy to achieve, but failed to materialise 19 Dec 2008

related whitepapers

today's top stories

What does Windows 7 mean for Microsoft?

With the sting of Vista still fresh, Redmond has to make next Windows work 10 Jul 2009

A smarter way to use BI

Getting the most from business intelligence systems requires not only careful management on the part of IT leaders, but also the committed involvement of decision-makers across the organisation 08 Jul 2009

Quenching a thirst for IT modernisation

A substantial restructure at soft drink supplier Nichols -­ purveyor of Vimto - ­led the company to update its software to Sage 1000 to replace its in-house application. This resulted in the streamlining of the IT department and an opportunity to customise the system 08 Jul 2009

How Satyam cleaned up its act

Chief executive CP Gurnani tells Angelica Mari why Tech Mahindra opted to keep the Satyam brand after it bought the scandal-hit services firm, and explains what the deal means for existing and prospective customers 09 Jul 2009

Lack of enterprise appeal takes shine off Chrome OS

Enterprise buyers unlikely to ditch Windows for Chrome OS in the near term, say experts 09 Jul 2009

Advertisement

Newsletter signup

Sign up for our range of FREE newsletters:

More available - click 'submit' to view

Existing User

Newsletter user login:

Advertisement

Jobs

Related jobs

Job of the week

Job alerts

Sign up here

Find your next job

IT Salary Checker

Check salary here

Advertisement

White papers

Search white papers

Top categories

VPN, Extranet and Intranet Solutions

WAN/ LAN Solutions

Network Security

Interoperability-Connectivity

Grid/ Utility Computing

Latest poll

Will Google Chrome OS be a genuine alternative to Windows?

Will Google Chrome OS be a genuine alternative to Windows?

Tell us your views on the new operating system rivalry

View poll results

Latest audio and video articles

network cablesVideo

How to maximise the value of your IT networking investment

A panel of experts discuss networking strategies that deliver real value to business 03 Jul 2009

green footprintsVideo

How to manage enterprise energy use - and the role IT can play

A panel of experts explore how firms can get to grips with their carbon footprint and make smarter use of energy 01 Jul 2009

Latest in-depth articles

Google ChromeAnalysis

Lack of enterprise appeal takes shine off Chrome OS

Enterprise buyers unlikely to ditch Windows for Chrome OS in the near term, say experts 09 Jul 2009

Satyam CEO CP GurnaniNews

How Satyam cleaned up its act

Chief executive CP Gurnani tells Angelica Mari why Tech Mahindra opted to keep the Satyam brand after it bought the scandal-hit services firm, and explains what the deal means for existing and prospective customers 09 Jul 2009

Advertisement

Primary Navigation